Gürtelstraße 31 - Completion Scheduled for March 2026
AUTHOR: Zunaira Erum

Gürtelstraße 31 remains on schedule, with construction progressing steadily across both the Garden House (House 2) and the Front Building (House 1). Completion is targeted for March 2026.

Front Building (House 1)


  • Windows and Roof: Installation works have been completed.
  • Building Services: Installation is ongoing and on track for completion by the end of July.
  • Drywalling: Interior partition works are currently in progress throughout the building.


Garden House (House 2)



Progress on House 2 includes:

  • Completion of window and roof installations.
  • Façade works currently underway, with completion expected by mid-July.
  • Basic building services—electrical, plumbing, and ventilation—fully installed.
  • Interior work in progress, with screeding being carried out.
  • Bathroom tiling scheduled for completion by end of September.


Visual Update



Two recent images document the current stage of construction:

  • Courtyard Side (Hofseitig – 11.06.25): Shows completed roof and window works with façade insulation in progress.
  • Street Side (Straßenseitig): Displays the front elevation and active material logistics.


Live Construction Monitoring

Real-time construction progress can be viewed via the live webcam feed.

Webcam link: Here